It has been announced that the reopening of the Botley Road - key to obtaining rental cars in Oxford at the station - will not happen at the end of August as was promised in January 2025 after previous delays.
There are further issues that will set back the opening at least a further 4 to 6 weeks. This is because 3 leaks in a gas line were discovered coincidentally with the bridge works, and that gas line now needs to be replaced.
A pedestrian walkway on the south side of the road under the bridge opened last week. This connection between the two parts of the severed road helps pedestrians, but there is no vehicle traffic.
We will see how accurate this new estimate proves, in the fullness of time.